Thursday, February 02, 2006
Construction to Start by March 2006
Onsite preparations for work by piling contractor Arabian Forasol have been underway for over a month, while approval issues are being worked out. Major construction will soon begin with excavations, shoring and piling, preceding the building of a raft type foundation:
Return to MAG 218 Community homepage.
- Early March: Start of excavation and shoring work, to continue 2-3 months. Shoring to a thickness of 800mm and excavation to a depth of 22 meters anticipated. Dewatering will be carried out at required depths.
- May or June: Installaton of ground anchors which limit latteral building movement.
- June or July: Piling, bored-type. This is when most of the piling work will be carried out, however, some piling will be performed at intermediate stages as well.
- July onwards: Construction of raft foundation. Allowing for an overlap of 2 or more weeks, the main contractor (yet to be appointed) will begin work on the foundation. At this stage of construction, plumbing, electrical and mechanical works will also commence.